Public Notification of a resource consent for the construction and operation of a resource recovery park at 30 Benmore Cresent, Manor Park
Hutt City Council has received an application from Waste Management (NZ) Ltd for a land use resource consent – RM230019 - for the construction and operation of a resource recovery park at 30 Benmore Cresent, Manor Park (legally described as Section 1, 6 SO 493901).
The resource recovery park will include the following activities on site:
Second-hand good store
Repair Café
Material Recovery Facility
Transfer Station
The applicant estimates that a maximum 145 staff will be required to operate the proposed facility, with 90 of these being truck drivers. This will see a progressive increase over time as theContinue reading
Hutt City Council has received an application from Waste Management (NZ) Ltd for a land use resource consent – RM230019 - for the construction and operation of a resource recovery park at 30 Benmore Cresent, Manor Park (legally described as Section 1, 6 SO 493901).
The resource recovery park will include the following activities on site:
Second-hand good store
Repair Café
Material Recovery Facility
Transfer Station
The applicant estimates that a maximum 145 staff will be required to operate the proposed facility, with 90 of these being truck drivers. This will see a progressive increase over time as the operation sees growth.
A summary of the proposed resource recovery park is provided below, however, please note that this is a summary only for full details please refer to section 1 (proposal) of the notification decision report on the right side of this page.
Building Bulk
To facilitate the operation of the proposal recovery park, the applicant is proposing 8 separate buildings be constructed on the application site, the proposed buildings will have the following characteristics:
Proposed Activity | Site Coverage | Building Height |
Retail and Café Building | 950m2 | 7m |
RTS Operations Warehouse | 3,750m2 | 12.9m |
B&C Operations Warehouse | 1,575m2 | 12.5m |
MRF Operations Warehouse | 2,250m2 | 12m |
Office Building | 410m2 (800m2 over 2 levels) | 10m |
Truck Workshop + Wash | 1025m2 | 12m |
Bin Wash Canopy | 300m2 | 8.9m |
Canopy | 750m2 | 6.8m |
Total | 11,010m2 | - |
Hours of Operation
The applicant is proposing the general hours of operation to be between 6.00am – 6.00pm, Monday – Sunday (7 days a week). With specific hours of operation being:
Mobile Machinery Operation: 7.00am – 5.00pm (Monday – Sunday)
Resource Recovery Park: 6.00am – 6.00pm (Monday – Sunday)
Some truck movements between 6.00am – 7.00am.
Additionally, the applicant (Waste Management (NZ) Ltd) provides municipal collections and collects waste from commercial clients. As a result the following vehicle movements may occur additionally:
2.00am – 5.00am: Up to 5 vehicle movements (weekdays)
5.00am – 6.00am: An expected 3 vehicle movements
6.00am – 7.00am: 12 trucks leaving the site (weekdays)
Vehicle Movements
The applicant has provided a Traffic Engineering Report (Appendix 10), which talks to the expected vehicle movements for the site per day. The report concludes that once the resource recovery park is fully developed the proposal will see a total of 604 vehicle movements a day, this will consist of 275 light vehicles and 329 heavy vehicles. As part of the Traffic Engineering report, the applicant has also projected an estimate of 870 vehicle movements a day by 2040. The following table summarises the proposed vehicle trips per day:

Additionally, the onsite parking will consist of the following:
Staff Carparking = 145 spaces, which is proposed to accommodate 55x office staff and 90x truck drivers and is inclusive of 20x EV charging spaces and allocated mobility parks.
Truck Parking = 80 marked spaces (70x medium rigid truck parks and 10x truck and trailer parks) inclusive of 25x EV chargers ‘plus’ additional hardstanding;
Cycling parking;
Staging
The proposed construction of the resource recovery park will occur over 2 stages, with the following being constructed/installed at each stage:
Stage 1
Weighbridge, transfer station, construction and demolition of buildings, public drop off area associated with the second hand goods store, bin storage area, office and administration block with staff amenities, car and truck parking, pavements and road, EV charging, truck and bin wash bay, service connections, water treatment, planting, dangerous goods store, fence, workshop, signage and the MRF operations building.
Stage 2
Waste compactors, C & D building, further EV charging points and any additional requirements required to comply with the conditions of the consent and/or to enhance site operation.
Earthworks
Land disturbance is proposed to level the site and create building platform for the proposed buildings. As a result, a maximum of 15,000m3 of earthworks is proposed to be undertaken. This will result in a less than 1.2m vertical change.
An assessment of the National Environmental Standards for Assessing and Managing Contaminant in Soil to Protect Human Health (NES-CS) for the proposed earthworks has been undertaken by Council, as a Detailed Site Investigation (DSI) provided by the applicant concluded that previous HAIL (Hazardous Activities and Industries List) had been undertaken on the site. These activities include:
Horticulture/ nursery activities
Potential fuel storage for quarrying
Timber storage yard
Metal blasting and protective coating
Uncontrolled demolition of former buildings
Concrete truck storage, quarrying vehicles and equipment
Clean-fill operations, undocumented fill
Burn-off Areas
As a result, the proposed earthworks will also require consent under the NES-CS.
For more details on the proposed resource recovery park please refer to the notification decision, assessment of environmental effects and associated documents found to the right of this page.
District Plan Breaches
The proposal requires resource consent for the following District Plan breaches (note: more details of these breaches can be found within the notification decision):
Controlled Activity – NESCS Regulation 9(1) (Contaminants)
Rule 8B 2.3(c) – Café (Restricted Discretionary Activity)
Rule 8B 2.3(a) – General Rules (Discretionary Activity)
Rule 8B 2.3(i) – Buildings within the Secondary River Corridor (Restricted Discretionary Activity)
Rule 8B 2.3(e) – Transfer Stations (Discretionary Activity)
Rule 8B 2.4(c) – Industrial Activity (Non-Complying Activity)
Rule 14A 5.1(c) – Transport (Restricted Discretionary Activity)
Rule 14B 2.4(a)(i) – Signs (Discretionary Activity)
Rule 14C 2.2(a) – Noise (Discretionary Activity)
Rule 14H 2.1(2) – Fault Hazard Area (Restricted Discretionary Activity)
Rule 14I 2.2(a) – Earthworks (Restricted Discretionary Activity
As the above activities are interlinked, Council has considered it appropriate to bundle the application into the more onerous activity status. The proposal is therefore assessed as a Non-Complying Activity.
Other Consents for the Application Site
Hutt City Council has received three other consents for the application site, being:
RM250052 – Subdivision consent for a 125-year lease over a portion of 30 Benmore Crescent
RM220258 – Land Use consent for bulk earthworks and construction of site office premises.
RM230018 – Land Use consent for bulk earthworks relating to the construction of roading and civil infrastructure.
Please note that these are being/have been processed separate to the above proposal and are not included for consideration as part of the public notification submission process for RM250019. For further information on these consents please refer to the information provided on Councils website, which can be accessed here.
Notification Process Information
The application includes an assessment of environmental effects and a range of supporting information and plans which can be viewed on the right hand side of this page. Please note the information present here includes the initial application documentation, information requests & responses and the most recent plan sit at the bottom.
Additionally, the application may be inspected at the following Council locations:
Council’s offices at 30 Laings Road, Lower Hutt: Monday to Friday, 9am – 4pm.
Koraunui Stokes Valley Community Hub at 184 Stokes Valley Road: Monday to Friday, 9:30am – 5:30pm and Saturday, 9am – 5pm.
Any person may make a submission on the application, but a person who is a trade competitor of the applicant may do so only if that person is directly affected by an effect of the activity to which the application relates that—
adversely affects the environment; and
does not relate to trade competition or the effects of trade competition.
You may make a submission by sending a written or electronic submission to:
Hutt City Council, Private Bag 31912, Lower Hutt 5040, or:
The submission must be in form 13, copies of this form are available to the right of this page.
You must serve a copy of your submission on Waste Management (NZ) Ltd (the applicant), as soon as reasonably practicable after serving your submission on Hutt City Council. Their address for service is as follows:
Waste Management (NZ)
97-99 Port Road
Seaview
Lower Hutt 5010
Att: Sarah Whiteman
Submissions close on 11 February 2026 at 5pm.
Form 12 - RM230019
Consent documents as originally lodged (now superseded)
-
APPLICATION - Archaeology Assessment.pdf (1.33 MB) (pdf)
-
APPLICATION - Assessment of Environmental Effects.pdf (1.65 MB) (pdf)
-
APPLICATION - Detailed Site Investigation.pdf (14.4 MB) (pdf)
-
Attachement 1 - Record of Title.pdf (841 KB) (pdf)
-
Attachement 2 - Site Layout Plans.pdf (2.09 MB) (pdf)
-
Attachement 3 - Earthworks Plans.pdf (2.56 MB) (pdf)
-
Attachement 4 - Civil Engineering Drawings.pdf (5.04 MB) (pdf)
-
Attachement 5 - Transportation Assessment.pdf (7.2 MB) (pdf)
-
Attachement 6 - Landscape Visual Assessment.pdf (13.9 MB) (pdf)
-
Attachement 7 - Three Waters Infrastructure Assessment.pdf (6.37 MB) (pdf)
-
Attachement 8 - Kiwi Rail Consultation.pdf (95.1 KB) (pdf)
-
Attachement 9 - Waka Kotahi Consultation.pdf (104 KB) (pdf)
-
Attachement 10 - Iwi Consultation.pdf (124 KB) (pdf)
-
Attachement 11 - GWRC (Flood Protection) Consultation.pdf (135 KB) (pdf)
-
Attachement 12 - Approved Earthworks Land Use Consent.pdf (3.49 MB) (pdf)
Further information requests and responses
-
01. 30 Benmore Crescent - s92 Response Letter - Potentialis Planning.pdf (6.22 MB) (pdf)
-
02. Addendum to AEE - Potentialis Planning (1).pdf (369 KB) (pdf)
-
03. Draft Construction Traffic Management Plan - Stantec.pdf (2.76 MB) (pdf)
-
03. Letter outlining the rationale for the traffic generation figures - Waste Management.pdf (89.1 KB) (pdf)
-
03. Traffic Memorandum - Stantec.pdf (236 KB) (pdf)
-
04. Crash Data Hebden Crescent SH58 RAB - NZTA.pdf (1.12 MB) (pdf)
-
05. Addendum to the Landscape and Visual Assessment - Boffa Miskell.pdf (7.47 MB) (pdf)
-
06. Lighting Plan and calculations - Advanced Lighting Technologies.pdf (1.59 MB) (pdf)
-
07. Air quality assessment report - PDP.pdf (1.87 MB) (pdf)
-
07. Draft Odour Management Plan.pdf (309 KB) (pdf)
-
08. Updated stormwater management plans - August 2023.pdf (3.38 MB) (pdf)
-
09. Plan showing proposed signs.jpg (266 KB) (jpg)
-
10. Acoustics and vibration email - Tonkin Taylor.pdf (57.6 KB) (pdf)
-
11. Email from Te Rūnanga o Toa Rangatira indicating support for the proposal.pdf (95.6 KB) (pdf)
-
12. Peer review on acoustics - Malcom Hunt.pdf (595 KB) (pdf)
-
13. Peer review on landscape effects - Isthmus Group.pdf (602 KB) (pdf)
-
13. Peer review on landscape effects addendum - Isthmus Group.pdf (387 KB) (pdf)
-
14. Peer review on transportation effects - Luke Benner.pdf (172 KB) (pdf)
-
15. Request to resume processing - Applicant.pdf (391 KB) (pdf)
-
15. Response to landscape peer review - Boffa Miskell.pdf (159 KB) (pdf)
-
15. Updated objectives and pols assessment.pdf (219 KB) (pdf)
-
15. Updated Site Services Plan.pdf (1.4 MB) (pdf)
-
15. Visual illustrations of landscaping - Boffa Miskell.pdf (13 MB) (pdf)
Updated application - January 2025
-
Updated Assessment of Environmental Effects - January 2025.pdf (2.28 MB) (pdf)
-
Appendix 1 - Schedule 4 Assessment.pdf (199 KB) (pdf)
-
Appendix 2 - Record of Titles.pdf (536 KB) (pdf)
-
Appendix 3 - District Plan Assessment.pdf (149 KB) (pdf)
-
Appendix 4 - Landscape and Visual Assessment Visual Simulations and Planting Plan - Boffa Miskell.pdf (13.2 MB) (pdf)
-
Appendix 5 - Faultline Study - Tonkin and Taylor.pdf (9.5 MB) (pdf)
-
Appendix 6 - Flood Assessment - River Edge Consulting.pdf (1.12 MB) (pdf)
-
Appendix 7 - Bulk Earthworks and Vegetation Removal Consent - RM220258.pdf (1.4 MB) (pdf)
-
Appendix 8 - Plans - Harris Architects.pdf (7.96 MB) (pdf)
-
Appendix 9 - Water Management Report - Spencer Holmes.pdf (2.98 MB) (pdf)
-
Appendix 10 - Traffic Assessment Report - Stantec.pdf (6.75 MB) (pdf)
-
Appendix 11 - Acoustic Assessment - Tonkin and Taylor.pdf (746 KB) (pdf)
-
Appendix 12 - Application for Servicing and Access - Spencer Holmes.pdf (962 KB) (pdf)
Public notification decision and plans
-
RM230019 - Notification Decision -SIGNED.pdf (3.51 MB) (pdf)
-
30 Benmore Crescent Conditions - 11.08.25.pdf (194 KB) (pdf)
-
2426 WMNZ Proposed Site Plan 19 Aug 2025.pdf (1.72 MB) (pdf)
-
2501 RTS Building for Planners RC3 19 Aug 2025.pdf (3.11 MB) (pdf)
-
2501 WMNZ BC for Planners RC3 - 19 Aug 2025.pdf (2.78 MB) (pdf)
-
2501 WMNZ MRF for Planners RC3 - 19 Aug 2025.pdf (2.8 MB) (pdf)
-
2501 WMNZ Office for Planners RC3 19 Aug 2025.pdf (3.39 MB) (pdf)
-
2501 WMNZ Retail for Planners RC3 - 19 Aug 2025.pdf (3.82 MB) (pdf)
-
2501 WMNZ RTS for Planners RC3 Aug 2025.pdf (3.09 MB) (pdf)
-
2501 WMNZ Truck - for Planners RC3 19 Aug 2025.pdf (3.62 MB) (pdf)
-
BM210903_Te_Karearea_BP_Plan_and_Sections_For_Information_20250717.pdf (3.41 MB) (pdf)
-
BM210903_Te_Karearea_BP_Plan_and_Sections_For_Information_BM210903_600.pdf (3.25 MB) (pdf)
-
BM210903_Te_Karearea_BP_Plan_and_Sections_For_Information_BM210903_601.pdf (241 KB) (pdf)
-
BM210903_Te_Karearea_RiverTrail_Concept_RC_20250821_reduce.pdf (2.73 MB) (pdf)
-
Changes to buildings at Waste Management site.pdf (86 KB) (pdf)